Posted on: April 3, 2018
A new 10 million gallon per day (mgd) firm capacity pump station is being designed to serve the existing Northeast Tank. Associated chemical feed systems include sodium hypochlorite, ammonia, and SeaQuest.
Posted on: April 2, 2018
Construction continues on this 25 million gallon per day (mgd) pumping station renovation while it remains in service. The first three of six pumping units are installed and will be started and tested. The new 13 kV electric service entrance, new 480V electrical switchgear, and standby diesel engine generator are completed, suction and discharge piping… Continue Reading
Posted on: April 1, 2018
BS&J is completing the design drawings and specifications for the construction of replacement water mains and other distribution system improvements in the SWNJ transmission and distribution system. Engineering services during construction will follow later in 2019.