Construction continues on this 25 million gallon per day (mgd) pumping station renovation while it remains in service. The first three of six pumping units are installed and will be started and tested. The new 13 kV electric service entrance, new 480V electrical switchgear, and standby diesel engine generator are completed, suction and discharge piping… Continue Reading
Posted on: April 1, 2018
BS&J is completing the design drawings and specifications for the construction of replacement water mains and other distribution system improvements in the SWNJ transmission and distribution system. Engineering services during construction will follow later in 2019.
Posted on: March 3, 2018
Construction is anticipated to begin later this year for the addition of updated water treatment processes for these two wells in Rockland County, NY.
Posted on: March 2, 2018
BS&J completed design and construction services for repairs to building columns originally designed by BS&J in the 1920s and constructed in the 1930s.
Posted on: March 1, 2018
Construction services by BS&J were completed for the construction of the third and fourth phases of District Metered Areas (DMAs) in the SWNY distribution system.
Posted on: February 1, 2018
BS&J is assisting with the evaluation, replacement and testing of the surge relief valve system at the Pompton Lakes Pumping Station serving the Aqueduct. In March and April 2018, BS&J assisted with the inspection services during the replacement of more than thirty (30) air/ vacuum valves for this 26 mile long Aqueduct before the Aqueduct… Continue Reading
Posted on: June 14, 2017
Submittals and shop drawings are being reviewed for pre-purchased equipment including the six (6) pumping units, electrical switchgear, and standby diesel engine generator. On-site construction is anticipated to start in July 2017. Work includes a new 13 kV electric service entrance, 480V electrical switchgear, outside piping modifications, and the new pumping units. During the work… Continue Reading
Posted on: May 2, 2017
Design and permitting services continue for the addition of updated water treatment processes for these two wells in Rockland County, NY.
Posted on: May 1, 2017
BS&J is preparing the design drawings and specifications for the construction of the fourth phase of District Metered Areas (DMAs) in the SWNY distribution system. Engineering services during construction will follow later in 2017.
Posted on: April 1, 2017
BS&J is assisting with the inspection and evaluation of building structures originally designed by BS&J in the 1920s and constructed in the 1930s.