SUEZ Water New Jersey Inc. – Distribution System Improvement Projects (March 2017)

Posted on: March 2, 2017

Having successfully completed the design of more than seven separate water main improvement projects in Bergen and Hudson County in 2015, 2016, and 2017, construction of these projects is scheduled the months of March through July 2017. This work requires attendance on-site, preparation of daily reports, photos, and field sketches, GIS location of installed assets,… Continue Reading

SUEZ Water Westchester Inc. – Villard Pump Station and Distribution System Upgrades (March 2017)

Posted on: March 1, 2017

This project involves replacing the pumping units in this station without taking it out of service. The existing station has two pumps with total capacity of 400 gallons per minute (gpm). A new three (3) pump skid will replace these pumps with total capacity of up to 1,000 gpm, providing more capacity to meet peak… Continue Reading

New Jersey American Water – Swimming River Water Treatment Plant Improvements (February 2017)

Posted on: February 1, 2017

In association with Gannett Fleming, BS&J is preparing applications and pursuing approvals for the required permits for the addition of a clearwell, pumping and outside piping improvements at this 36 million gallon per day (mgd) water treatment plant.

SUEZ Water New York Inc. – District Metered Area Project, Phase 3 (January 2017)

Posted on: January 1, 2017

Having successfully completed phases one and two, BS&J is preparing the design drawings and specifications for the construction of the third phase of District Metered Areas (DMAs) in the SWNY distribution system. Engineering services during construction will follow later in 2017.

SUEZ Water New Jersey Inc. – Inspection of the Wanaque South (Oradell) Aqueduct (December 2016)

Posted on: December 1, 2016

An external visual inspection and inspection of the valve and access vaults were completed by SWNJ and BS&J personnel. BS&J prepared a report evaluating the findings and prioritizing the recommendations.

SUEZ Water New Jersey Inc. – Formal Dam Inspections (November 2016)

Posted on: November 1, 2016

BS&J completed the Formal Inspections of Oradell Reservoir and Lake Tappan Dams, and the Regular Inspections of Woodcliff Lake and Lambertville Dams.

SUEZ Water New York Inc. – Ramapo Valley Well Field (September 2016)

Posted on: September 1, 2016

Design and permitting continues for the addition of ultra-violet light disinfection at Well No. 97. A platform is required to support the existing and new equipment above the design flood elevation.

Suez Water Westchester – Eastchester Rd Water Main Design and Construction Inspection Services (June 2016)

Posted on: June 2, 2016

Approximately 2,800 linear feet of 16 inch diameter water main installation to replace an existing 12 inch water main along a heavily traveled thoroughfare in Eastchester required design, permitting, and constructions services provided by BS&J. Meeting the aggressive project schedule to design, construct, and place in service within six (6) months was a critical project… Continue Reading

Suez Water Rahway – Asset Management Plan (June 2016)

Posted on: June 1, 2016

BS&J is preparing an Asset Management Plan for Suez Water Rahway. Components of the plan include: conducting an asset inventory and condition assessment, establishing the required level of service, identifying critical assets, preparing life cycle costs, developing a long-term funding strategy, and summarizing this information in an asset management report.

Middlesex Water Company – Carl J. Olsen WTP, Filter to Clearwell External Pipe Condition Assessment (May 2016)

Posted on: May 3, 2016

Existing shop drawing submittals in BS&J’s files from the original construction in 1968, visual inspection and ultra-sonic thickness measurements in May 2016 were instrumental in assessing the condition of these welded steel pipes. BS&J prepared recommendations for MWC review for continued service.