Submittals and shop drawings are being reviewed for pre-purchased equipment including the six (6) pumping units, electrical switchgear, and standby diesel engine generator. On-site construction is anticipated to start in July 2017. Work includes a new 13 kV electric service entrance, 480V electrical switchgear, outside piping modifications, and the new pumping units. During the work this 25 million gallon per day (mgd) station will remain in operation.